Gantry crane rail installation

Gantry crane rail installation method I – pressing plate fixing method

Lay the guide rail directly on the concrete support beam and fix it with a fishtail pressing plate. The original old workshop adopts this installation method, and the rail support and plant pouring are completed. This installation method has the advantages of stable lifting operation, low vibration, and noise, large cross-sectional area of the support beam, and some are also equipped with pedestrian passages, which are convenient for inspection and maintenance of rails, easy to find, and solve.

Gantry crane rail installation method II – sleeper fixation method

This method is applicable to the hanging of the door lines on the construction site. After the stone is paved, the guide rail is paved. Generally, the cross-section size of the sleeper is 200 ~ 300mm, and the spacing is generally about 600 ~ 800mm. The fixing mode of the invention is more convenient to disassemble and move.

Gantry crane rail installation method III – hook bolt fixation method

At present, it is used in the construction of metal structure workshops. The support block is welded on the workshop column, the support block is paved with I-steel, and then the I-steel is used as the guide rail and fixed by screw or welding. Because the pillars and supporting beams are of metal structure, they have large vibration and noise in hoisting operations and small maintenance space. The pillars are required to be firm and stable, and the construction is simple and fast.

Comments

Popular posts from this blog

Study on Cooling Method of SUP9 Spring Flat Steel

Study on Cooling Method of SUP9 Spring Flat Steel Hot rolled spring flat steel bar is mainly used for the automotive industry, and it’s the raw material for automobile leaf spring  manufacturing. The main varieties of spring steel include 60Si2Mn spring steel,  SUP9 spring steel flat bar , 55SiMnVB spring steel. SUP9 spring steel flat bar is produced in accordance with the Japanese standard. At present, many leaf spring manufacturers mostly use SUP9 spring steel as the raw material for manufacturing automotive leaf springs. Compared with 60Si2Mn, SUP9 spring steel has good hardenability and low decarburization tendency, so the mechanical properties and fatigue properties of the leaf springs produced with SUP9 spring steel are better than that of 60Si2Mn steel. However, due to the good hardenability of  SUP9 steel , the hardness is often too high during actual rolling production and cooling. The reheating, quenching and tempering treatment are carried out in...

Development of A32 and A36 High Strength Shipbuilding Steel Plates

Development of A32 and A36 High Strength Shipbuilding Steel Plates Since the 1990s, China’s  shipbuilding steel plates  industry has entered the international market on a large scale, and the shipbuilding steel plates industry has gradually become one of the pillar industries in China. With the development of shipbuilding steel plates in the direction of large-scale and light-weight, the general strength ship plates can no longer meet the needs of the hull, and the proportion of high-strength ship plates will continue to increase. Therefore, the development of high-strength shipbuilding plates has broad market prospects. Structural steel for hull can be divided into general strength steel and high strength steel. A32 and A36 are one type of structural steel for high strength hull. With the development of the shipbuilding industry, the requirements for materials are becoming more and more demanding. At present, in the factory approval, besides the certification of the ...

Rail clip installation

Rail clip installation rail clip installation Prerequisites for the rail clip installation 1. The rail presser is installed after the steel beam on the crane rails surface is adjusted; 2. The steel beam of the crane must be 3. The rail pressure device should be installed; 4. Before the installation of the  rail clamp , the surface paint of the crane beam is finished and meets the requirements of the current regulations; 5. Before the installation of the rail presser, the track joints should be connected, and the track joints and side bending deviations should meet the requirements of “Steel Structure Engineering and Acceptance Specifications”-83). 6. The welding of the base plate control plate and the steel suspension beam should meet the design requirements. Installation sequence and essentials A. Welding the fixed base, the fixed base can be used, the three grooves on the surface and the position of the rail presser can be positioned, and the allowable deviation of the position ...