Skip to main content

Welding of Crane Rail Flat Steel and Q235 Steel

Welding of Crane Rail Flat Steel and Q235 Steel
The fixing of the crane rail flat steel is not fixed by the common pressing plate, but the crane rail steel flat is welded to the bottom plate, and then the bottom plate is bolted to the upper steel structure of the slow cooling pit, so that the crane rail flat steel can be fixed to the upper steel structure of the slow cooling pit. The higher carbon equivalent causes strong harden tendency of the workpiece during the rapid cooling process after welding, and a hard and brittle martensite structure appears in the heat affected zone of the base metal, especially near the weld line. Under the action of welding stress, the tensile strength of the hard and brittle martensite structure is exceeded, causing it to crack and generate cold cracks. Welding of crane rail flat steel and Q235 low carbon steel belongs to dissimilar steel welding. Q235 steel is a kind common carbon structural steel with good weldability. The crane rail flat steel is usually high carbon steel, and the hot shadow area after welding is prone to cold cracks. Therefore, the welding of the crane rail flat steel and the Q235 low carbon steel is mainly to solve the problem of cracks generated after the welding of the rail heat affected zone. According to the general welding specifications, for the welding of carbon steel of different strength grades, the welding material should be selected to ensure that the tensile strength of the weld metal, which should be higher than or equal to the lower limit of the parent metal standard on the lower strength side.
Before welding, the rust, oil, moisture and other impurities within 50mm on both sides of the weld should be removed. For electrode arc welding, the electrode needs to be baked at 350°C for 1 hour, and it can be used as needed. For CO2 gas shielded welding, it is necessary to put the CO2 gas cylinder upside down and drain the water in the bottle to check that the dryer is in good condition. Before welding, the crane rail flat steel side was heated to 350°C with an oxyacetylene flame within 100 mm, and the temperature was measured by the temperature measurement ratio. Then welding should be according to certain parameters, continuous welding is to ensure that the interlayer temperature is not less than the preheating temperature. After welding, the weld bead and the side of the crane rail flat steel base material should be slowly cooled with aluminum silicate fiber felt immediately. After cooling to room temperature, the weld should be inspected, and after the coloration flaw detection, no cracks were observed in the arc welding of the electrode. However, there was crack in the middle of the arc-welding section of the first weld side with the CO2 gas shielded welding. On the second day of the arc welding of the electrode, crack was found in the heat-affected zone on the side of the rail appeared crack along the fusion line. After the arc welding of the electrode, there is a delayed crack in the heat affected zone of the rail. It may be because of the uncomplete slow cooling after welding. After the welding, the aluminum silicate fiber felt does not completely wrap the crane rail flat steel, and the martensite structure is hardened in the heat-affected zone, and steel rail cracks under the welding stress. The CO2 gas shielded welding heat is concentrated, the heat affected zone is narrow, and the hardening tendency is small, so there is no crack in the heat affected zone of the rail. However, for the welding lines s on both sides of the crane rail flat steel, cracks appear in the middle of the weld side of the former welding, which is caused by the simultaneous weld lines welding of the welds on both sides. When the first weld side weld is not completely crystallized, the other side begins to weld. Under the welding stress of the back weld side, the weld on the weld side is not completely crystallized and cracked, so that cracks will not appear in the middle of the welding line.

Comments

Popular posts from this blog

Principle of rail clamp design

Principle of rail clamp design rail clamp design The rail clamp design has several functional features: 1. Adjustability: The adjustable length is 15mm, and its adjustability functions include: (1) The rail presser is easy to install, saves time, and has high precision (2) The track can be adjusted if the structure of the support beam is slightly changed. 2. Anti-loosening: Under the action of the lateral force of the track, through the force analysis of the welding RTYB, a part of these lateral forces are transmitted to the bottom seat through the upper cover plate as the pressure of the bottom edge to seat on the upper cover plate. The other part is the lateral friction between the base and the upper cover. Since the wedge-shaped action between the base and the upper cover plate is converted into the tightening force of the bolts, it has an anti-loosening effect. 3. Self-locking: The three pieces are self-locking together through the interaction of the upper cover, the base, and the

steel chamfer / triangular steel bar supplier from China- Glroysteelwork

steel chamfer / triangular steel bar supplier from China- Glroysteelwork Steel chamfer is manufactured from cold drawn steel and can be welded or bolted into place to provide relief from sharp edges to reduce chipping and spalling.Steel chamfer is available in three sizes: 10mm*10mm15mm*15mm20mm*20mm25mm*25mm Glorysteelwork is an professional manufacture of cold drawn, we have many years export experiences and long term cooperation clients. Materials: SS400/A36/Q235B Length:4000mm or as required Contact Us E-mail: info@glorysteelwork.com Whatsapp:86 15036167067 Mobile: 86 15036167067 Skype: karenwu7067

What is rail creep

What is rail creep rail creep Rail creep is also known as line crawl. The creeping phenomenon of the rail along the longitudinal direction of the line. With the increase in railway transportation tasks, the impact of the wheels on the rails when the train is running accelerates the creep of the rails. Rail creep can cause many diseases of the line. In order to prevent the occurrence of track creep diseases, it is necessary to find out the real cause of creeping in order to effectively eliminate the problem. There are two different manifestations: the rails move along the soft sleeper surface due to insufficient fastening pressure of the fasteners; the longitudinal movement of the row is caused by insufficient ballast bed resistance. The reason for this is the longitudinal force of the rail caused by the wheel rolling and longitudinal slip, train braking, the change of rail temperature, and the creep caused by the deflection and deformation of the rail under the action of the wheel load